Privately prepared information — not an official Council notice. Review the official documents, form your own view and write in your own words.
HightonVoice.orgPP-909/2025 · Roslyn Road, Highton

How this application got here

Nine months of assessment, then a few weeks for the public. The sequence is worth seeing laid out.

Dates below are taken from Council’s planning register, from date-received stamps on the advertised documents, and from Council’s own project pages. Where a date is not established, it is not shown.

  1. 13 October 2025

    PP-825/2025 lodged — a two lot subdivision and removal of an easement at the same parent address.

  2. 31 October 2025

    PP-909/2025 lodged — this application. Nine months before the public was invited to comment.

  3. 3 December 2025

    Acoustic consultant inspects the site and records background noise over approximately one hour.

  4. 9 January 2026

    PP-825/2025 permit issued, under Delegated Authority. No councillor voted on it.

  5. 16 January 2026

    PP-29/2026 lodged — a three lot subdivision at the same parent address.

  6. 12 February 2026

    PP-102/2026 lodged — construction of ten dwellings at the same parent address.

  7. 23 February 2026

    Acoustic report received by Council.

  8. 26 February 2026

    PP-825/2025/A lodged, seeking to amend the subdivision permit.

  9. Early 2026

    Council completes works at the Roslyn Road and Thornhill Road intersection, including a roundabout and raised pedestrian crossings, with stated objectives including improved safety near Highton Primary School.

  10. 19 March 2026

    Amended permit issued for PP-825/2025/A, adding creation of a restriction.

  11. 18 June 2026

    Council issues a request for further information on this application.

  12. 22 June 2026

    The applicant meets Council’s Special Building Overlay engineers. An increase of 0.05 m to the dwelling’s finished floor level is agreed.

  13. 10 July 2026

    The applicant responds. Civil drawing sets, an updated peer review letter, updated architectural drawings and an updated planning assessment report are lodged with Council. Most of those drawing sets are not published in the advertised list.

  14. July 2026

    Public notice begins. A sign goes up on the fence and the application appears on Council’s advertised planning page.

  15. 6 August 2026

    Public comment closes. Council states it will not decide before this date. Submissions received afterwards will be considered if a decision has not yet been made.

What the sequence shows

The application was lodged at the end of October 2025 and advertised in July 2026. Council and the applicant spent roughly nine months on it — a request for further information, a meeting between engineers, revised drawings, a revised planning report. The public gets a few weeks at the end, and the version being advertised is the version that survived that process.

That is not a criticism of anyone. It is how the system is built, and there are good reasons for an applicant and a council to work through technical detail before a proposal is put to neighbours. But it is worth knowing when you read the documents: what you are looking at is the refined version, and the reasoning that shaped it — Council’s requests, Council’s engineering comments, the meeting in June — is largely not in front of you.

Sources: City of Greater Geelong planning register; date-received stamps on the advertised documents; FI – RFI Response Letter, 10 July 2026; Acoustic Report; Council and Transport Victoria project pages; Council’s current application page.

Have your say before Council decides

Council currently lists 6 August 2026 for public comment. Submit as early as you can. Council states that a submission received after that date may still be considered if it arrives before Council makes a decision — but do not delay if you can submit now.

Read the documents and make your submissionOpens Council’s official application page

Not sure what to write? Council only acts on certain kinds of concern. Our three-question helper turns what bothers you into the language Council actually weighs — then you paste it into their form.

Council says objections and letters of support are public documents, and that the submitter’s name and postal address may be viewed, excluding contact details.